DATABASE MIGRATION EXPERIENCE

SQL Server & Database Migration Case Studies

Real-world migration experience across SQL Server upgrades, Azure modernization and complex cross-platform database migrations. 

Migration Experience at a Glance

Eight selected Everconnect migration projects demonstrate experience across SQL Server upgrades, Azure modernization, Snowflake, Azure Data Lake integration and complex cross-platform database migrations.

Featured Database Migration Case Studies

These anonymized projects show how Everconnect has approached SQL Server upgrades, Azure modernization, Snowflake modernization, Azure Data Lake integration and complex cross-platform database migrations in production environments.

Building an Azure Data Lake for Healthcare Analytics Without Moving Production Systems

Healthcare organization | On-premises SQL Server to Azure Data Lake with Azure Data Factory

Everconnect helped a healthcare organization build an Azure data foundation for data warehousing and reporting. Eight on-premises SQL Server OLTP database servers stayed in production while Azure Data Factory pipelines moved data into Azure Data Lake. The same analytics flow also took in EDI exchanges, three FTP sources, file drops and invoice information read from emailed PDF attachments.

The project covered roughly 25 to 40 databases and 300 to 500 source tables, an initial historical load of about 2 to 4 TB, and 2 to 5 million new or changed rows per day through 30 to 50 pipelines. Roughly 250 to 600 EDI and other files per day and 1,500 to 3,000 emailed PDF invoices per month joined the flow, feeding 20 to 35 reports and dashboards.

Result: The organization kept its on-premises SQL Server OLTP environment while ADF pipelines moved data into Azure Data Lake for data warehousing and reporting. No quantified improvement in reporting speed, cost or manual effort is claimed.

Read the full Azure Data Lake and Azure Data Factory case study or see our ETL and data integration services.


Modernizing a Complex Enterprise Data Warehouse with Snowflake

Consumer Products — Manufacturer and Distributor | SQL Server to Snowflake on Azure

Everconnect moved the company’s on-premises SQL Server data warehouse, built on SSIS packages, stored procedures, scheduled file transfers and spreadsheet adjustments, to Snowflake on Azure. The warehouse combined regional ERP systems, distributor sales feeds, inventory applications and customer-order platforms, with business rules spread across stored procedures, ETL packages and spreadsheets.

Instead of copying the old design, the team redesigned the pipelines, reworked SQL Server-specific procedures into set-based Snowflake SQL, preserved effective-dated history and tested well beyond row counts: financial reconciliation, failure and restart scenarios, security and parallel business validation. Reporting domains moved in stages while the legacy warehouse stayed available during acceptance.

Result: Finance gained confidence in the numbers because reconciliation became part of every cycle, historical corrections no longer meant rebuilding the whole warehouse, and new automation replaced manual file handling: automatic distributor-file intake, exception routing, freshness monitoring, controlled publication and scheduled business outputs.

Read the full Snowflake case study or see our Snowflake consulting services.


Moving Manufacturing Databases to Azure Without Measurable MES Latency Impact

Company AC | Manufacturing — Industrial Components | ~850 employees | Columbus, OH

Everconnect migrated the manufacturer’s SQL Server 2016 SP2 Standard environment to SQL Server 2022 on Azure VMs. The environment included 3 servers, 3 SQL Server instances, 22 databases and 1.6 TB of data, with the largest database at 720 GB.

Critical dependencies included Epicor ERP, a manufacturing execution system (MES), Power BI, SSIS supplier EDI feeds and plant historians. More than 40 SSIS packages contained hard-coded server names, while plant-floor traffic was sensitive to network latency.

Result: The production migration recorded 45 minutes of downtime with no measurable impact on MES latency. SSIS packages were standardized using environment parameters, and infrastructure costs were reduced by 22%.


Modernizing Healthcare Reporting and Improving Disaster Recovery

Company AA | Healthcare — Regional Hospital Network | ~4,200 employees | Sacramento, CA

Everconnect migrated the hospital network’s SQL Server 2016 SP3 Enterprise environment to SQL Server 2022 on Azure VMs with Always On availability groups. The environment included 6 servers, 6 SQL Server instances, 48 databases and 3.8 TB of data, with the largest database at 1.4 TB.

Dependencies included Epic Clarity extracts, an HL7 interface engine, 220 SSRS reports, nightly SSIS loads and Active Directory. Migration planning also had to account for HIPAA controls, TDE certificates, collation mismatches in three legacy databases and a heavily fragmented 1.4 TB reporting database.

Result: Reporting performance improved by 35%, six aging servers were retired, and the disaster recovery RPO improved from 24 hours to 15 minutes through a cross-region Always On availability group replica.


Consolidating a 42 TB Insurance Estate onto SQL Server

Company AD | Insurance — Property & Casualty | ~12,500 employees | Chicago, IL

Everconnect migrated a large Sybase ASE estate to SQL Server 2019 Enterprise on VMware. The source environment included 18 servers and 310 databases totaling 42 TB, with the largest database at 9.8 TB.

The environment supported a Guidewire policy system, actuarial SAS models, mainframe DB2 feeds, Informatica ETL and more than 600 cron/Autosys jobs. The cross-platform conversion also involved T-SQL differences across more than 2,000 Sybase stored procedures and differences in transaction behavior.

Result: The migration was completed across five waves with four hours of downtime per wave. Eighteen servers were consolidated to six, approximately $410,000 per year in licensing costs was eliminated, and month-end close was reduced from three days to 1.5 days.

Representative Database Migration Experience

Eight selected projects illustrate the range of company sizes, platform changes and production constraints in Everconnect’s migration experience. Client names are anonymized, and company sizes are approximate.

IndustryCompany SizeMigration / ModernizationScaleRecorded Outcome
Manufacturing — Industrial Components~850 employeesSQL Server 2016 SP2 Standard → SQL Server 2022 on Azure VMs22 databases / 1.6 TB45-minute downtime; no measurable MES latency impact; infrastructure cost reduced 22%
Healthcare — Regional Hospital Network~4,200 employeesSQL Server 2016 SP3 Enterprise → SQL Server 2022 on Azure VMs with Always On AG48 databases / 3.8 TBReporting 35% faster; six aging servers retired; DR RPO improved from 24 hours to 15 minutes
State Government — Health & Human Services Agency~30,000 employeesSQL Server 2016 SP3 Enterprise → Azure SQL Managed Instance, Business Critical, Azure Government410 databases / 68 TBZero benefits-processing outages; 22 instances consolidated to 6 managed instances; patching effort reduced 70%; determinations 2× faster
SaaS — Marketing Analytics~65 employeesSQL Server 2016 SP2 Standard in colocation → SQL Server 2025 on Azure VMs120 databases / 1.1 TB10-minute cutover; all 120 tenants migrated with scripted automation; colocation exited; hosting cost reduced 38%
Insurance — Property & Casualty~12,500 employeesSybase ASE 15.7 → SQL Server 2019 Enterprise on VMware310 databases / 42 TB18 servers consolidated to 6; approximately $410K/year licensing savings; month-end close reduced from 3 days to 1.5 days
Logistics — Freight & Trucking~2,800 employeesIBM Db2 for i on IBM i / AS/400 → SQL Server 2022 Enterprise with Always On AG36 databases / 5.5 TBAS/400 retired; ingestion 3× faster; dispatch screen reduced from 6 seconds to under 1 second; RPG skills dependency removed
Consumer Products — Manufacturer and DistributorNot disclosedOn-premises SQL Server data warehouse with SSIS → Snowflake on AzureRegional ERP, distributor, inventory and order sourcesStaged cutover with parallel runs; reconciliation built into every cycle; new automation for file intake, exception routing and reporting
Healthcare — Analytics Data FoundationNot disclosedOn-premises SQL Server OLTP (retained in production) plus EDI, FTP, file and PDF invoice data → Azure Data Lake with Azure Data Factory25–40 databases / 4–7 TB source; 2–4 TB initial loadProduction SQL Server stayed in service; Azure Data Lake foundation for data warehousing and reporting

About these examples: Project results are specific to each environment and are not guarantees for another migration. Downtime measurements have different scopes and should not be compared directly across projects.

What These Database Migration Projects Have in Common

The technology and scale vary, but the recurring challenge is the relationship between the database and the business systems around it. Successful database modernization requires more than moving database files. Applications, integrations, jobs, security, recovery requirements and business downtime all influence the migration plan.

1. Discover the Database Estate and Its Dependencies

Start by identifying versions, editions, servers, instances, databases, sizes, owners, applications, logins, jobs, linked servers, reports and ETL processes. Dependencies outside the database engine can materially affect the migration.

For example, Company AC had more than 40 SSIS packages with hard-coded server names, while Company AD’s environment included more than 600 cron and Autosys jobs.


2. Assess Compatibility and Select the Target Architecture

Evaluate application-vendor support, database features, code compatibility, transaction behavior, security requirements, licensing and operational needs before selecting a destination.

The right answer may be a newer version of SQL Server, SQL Server on Azure VMs, Azure SQL Managed Instance or another architecture. The projects on this page demonstrate multiple destinations rather than one universal migration path.


3. Design Recovery, Downtime and Migration Sequencing

Define the downtime the business can tolerate along with recovery time and recovery point objectives. Capacity, connectivity, encryption, HA/DR and application boundaries can determine whether the migration should occur as a single cutover or in multiple waves.

Company AD used five migration waves. Company AA’s target architecture included a cross-region Always On availability group replica to improve disaster recovery.


4. Test and Rehearse Before Production Cutover

A migration plan should include representative application testing, integration testing, data validation, performance testing and a timed rehearsal before production cutover.

The selected projects demonstrate why this matters. Company AA required separate attention to SSRS subscriptions, while Company AC needed plant-floor network latency considered before selecting and validating the Azure environment.


5. Define Cutover and Rollback Decisions

A production migration should have clear ownership, go/no-go criteria, validation steps, rollback triggers and a defined recovery path. The migration team should also determine how new writes and application activity will be handled during the transition.

The appropriate cutover method depends on the source platform, target architecture, data volume, change rate, dependencies and acceptable outage window.


6. Validate the Business and Plan Ongoing Database Support

Migration is not complete simply because the databases are online. Validate critical transactions, reports, jobs, integrations, application behavior, performance and recovery against agreed acceptance criteria.

After handoff, establish responsibility for monitoring, backups, patching, performance and incident response. Everconnect provides ongoing SQL Server consulting and managed database support when continued DBA expertise is needed after a migration.

Start with evidence: A useful migration plan connects each technical change to an application owner, a business constraint and an acceptance test. That makes migration risk, sequencing and production cutover decisions easier to evaluate.

Planning a SQL Server migration or upgrade?

Before making changes to production, get a clearer picture of what you’re working with. Everconnect Data System’s interactive SQL Server Migration & Upgrade Readiness Assessment helps identify potential complexity, dependencies, downtime requirements, recovery considerations and preparation gaps.

No database access is required, and it only takes a few minutes.

Database Migration Questions from Business and IT Leaders

Organizations planning a SQL Server upgrade or database migration often face the same fundamental questions: where to move, what could break, how much downtime to expect and how to determine whether the environment is actually ready. The answers depend on the applications, dependencies, recovery requirements and business processes surrounding the databases.

What should we do if SQL Server 2016 is still in production?

Start with an assessment of the SQL Server versions, applications, dependencies, compatibility requirements and recovery environment. From there, compare modernization options such as upgrading SQL Server on-premises, moving SQL Server to Azure VMs or evaluating managed Azure database services.

Everconnect’s representative migration experience includes SQL Server 2016 environments modernized to SQL Server 2022 on Azure VMs as well as SQL Server 2016 environments moved to Azure SQL Managed Instance.


Should an older database be upgraded, moved to Azure or replaced?

The age of the database platform is a reason to assess the environment, but it is not enough information to choose the destination. Consider application-vendor support, database features, code compatibility, network latency, recovery requirements, security, operations and cost.

Keeping SQL Server can reduce application change, while changing database platforms can require substantial code and data conversion. The right architecture depends on the workload and business requirements rather than one standard modernization path.


How risky is a production SQL Server upgrade?

Risk depends on what must continue working and how thoroughly the change has been assessed and tested. Important areas include application compatibility, permissions, encryption keys and certificates, collations, SQL Agent jobs, SSIS packages, linked servers, reports, integrations, performance and recoverability.

For example, one Everconnect healthcare migration required TDE certificate sequencing, resolution of legacy collation differences and separate consideration of SSRS subscriptions. A production migration plan should include testing, validation, cutover criteria and a defined recovery path.


What is the safest approach when several older SQL Servers need upgrades?

Begin by mapping the environment and its dependencies. Group workloads into manageable migration units based on applications, business ownership, technical dependencies and acceptable downtime.

Larger environments may benefit from phased migration waves rather than one large cutover. One representative Everconnect project involving 310 databases and 42 TB was completed across five migration waves. The appropriate sequencing depends on the individual environment.


What about applications, SQL Agent jobs, SSIS and other integrations?

They should be included in the migration assessment from the beginning. A useful dependency inventory can include application connection strings, SQL Agent jobs, service accounts, linked servers, SSIS packages, reporting services, ETL processes, scheduled tasks and external interfaces.

The projects represented on this page include environments with more than 40 SSIS packages containing hard-coded server names, 220 SSRS reports, nightly SSIS workloads and more than 600 scheduled cron and Autosys jobs. Moving the databases alone does not validate that the surrounding business systems will work correctly after migration.


How can we keep database migration downtime as low as possible?

First define the outage window the business can tolerate. Then select a migration method appropriate for the source platform, target architecture, database size, data-change rate and validation requirements.

Rehearsing the final synchronization and application cutover can help identify problems before production migration. Across the representative projects on this page, recorded downtime included 10 minutes for one SaaS migration, 45 minutes for a manufacturing migration and under 15 minutes per database for a large government migration. These are individual project results, not guaranteed downtime targets for another environment.


Can Everconnect help us choose the right Azure database architecture?

Yes. Everconnect can assess the existing database environment and help evaluate target architectures based on application compatibility, operational requirements, capacity, connectivity, security, availability and recovery objectives.

Everconnect’s representative experience includes migrations to SQL Server on Azure VMs and Azure SQL Managed Instance. The appropriate Azure architecture should be selected based on the requirements of the specific workload rather than assuming one Azure database service fits every environment.


What should a mid-sized business look for in a US-based database migration consultant?

Look for relevant project evidence, technical ownership, experience with your database platform, an application-aware assessment process, a testable cutover plan and clearly defined support responsibilities.

Everconnect Data Systems is a California-based database consulting company serving organizations across the United States. Its representative migration experience includes an approximately 850-employee manufacturer whose SQL Server 2016 environment was migrated to SQL Server 2022 on Azure VMs with 45 minutes of recorded production downtime and no measurable impact on MES latency.


Should we complete an assessment before committing to a database migration?

Yes. Before committing to a migration plan, establish what is running, what depends on it, which target architectures are viable and what must change.

A professional migration assessment should examine areas such as compatibility, dependencies, target architecture, migration sequencing, downtime, recovery and validation. Everconnect’s interactive SQL Server Migration & Upgrade Readiness Assessment is a useful starting point for identifying questions and unknowns; a professional technical assessment is used to validate the actual environment and define the project.


Can Everconnect assess, migrate and support our SQL Server environment afterward?

Yes. Everconnect provides database assessments, migration services, SQL Server consulting and ongoing managed database support.

A migration engagement can include assessment and discovery, architecture and migration planning, implementation, validation and handoff. Ongoing DBA support can also be included when the organization needs continued assistance with monitoring, backups, performance, maintenance, patching or database incidents after the migration.

Planning a SQL Server Migration or Upgrade?

Everconnect can help assess your current environment, identify migration risks and dependencies, select the right target architecture, and plan and execute the migration with production downtime and business continuity in mind.

Start with our interactive SQL Server Migration & Upgrade Readiness Assessment, or talk with our database team about your environment..